**Short version:** almost all of NVIDIA's revenue is now data centre, and the new Vera Rubin generation is shipping. Figures are from NVIDIA's Q3 FY2027 release for the quarter ended 25 October 2026.

The numbers
| Line | Q3 FY27 | vs Q2 | vs a year ago |
|---|---|---|---|
| Revenue | $115.8B | +20% | +103% |
| Data centre | $107.6B | +21% | +110% |
| Edge computing | $8.2B | +14% | +42% |
| Gross margin (GAAP) | 74.8% | ||
| Gross margin (non-GAAP) | 74.9% |
NVIDIA now reports two segments, data centre and edge computing; gaming and other lines are not broken out separately in this release.
The outlook
Q4 revenue is guided at $130.0 billion, plus or minus 3%. Two details matter: the quarter has an extra week, and NVIDIA assumes no data-centre compute revenue from China. Read the jump with both in mind.

What it means if you buy or rent GPUs
- Vera Rubin is real. The release says Vera Rubin NVL72 has shipped with the fastest ramp in company history. Cloud availability of Rubin instances will follow the big buyers first.
- Blackwell stays the workhorse. For most teams renting capacity in 2027, Blackwell-generation instances will be the realistic option; plan budgets on them.
- **Local AI is a separate line.** Desk-side machines like RTX Spark and the DGX Spark HPC kit sit in a different market from these data-centre numbers.
The quarter was presented by interim CEO Colette Kress; for the leadership story see Jensen Huang's resignation and return. If you would rather not depend on rented GPUs at all, our guides to running LLMs locally and self-hosting Ollama with Open WebUI are the practical next step.